Between October 2024 and May 2026, Peabody Energy consistently presented the Centurion mine as a high-performing asset. Management promised production would hit 700,000 tons in the first quarter of 2026 and maintained a full-year output projection of 3.5 million tons. By the time the company released its actual results, those figures had collapsed to 250,000 tons and 2.5 million tons, respectively. Costs for the metallurgical coal segment spiked to $142 per ton, far exceeding the initial $113 guidance.
The lawsuit, filed by Levi & Korsinsky, LLP, alleges these discrepancies were not mere operational hiccups but the result of reckless oversight. The complaint points to the use of equipment that had sat dormant for eight years, which suffered mechanical failures, conveyor breakdowns, and roof control issues upon deployment. These technical failures resulted in an $80 million swing in the company's met coal segment EBITDA, turning projected growth into a $7 million loss.